We have mentioned before about the struggle we've had in getting our building permit for the dorms. We thought we had it last month; then when I went to pick it up I was told more information was needed. So we engaged the services of an engineer in Puerto Cortes. We were not very optimistic about getting the information quickly and I had to leave Honduras no later than May 9. Well, as it turned out, the engineer had the information ready at four o'clock on the afternoon of May 8. Nicholas and I met him along the highway, got the documents, and took them to the municipality before they closed. Next day I left Honduras and Nicholas returned to the municipality. He was given the amount that we would have to pay in order to get a permit. We discussed it over the phone, and since the amount was not entirely unreasonable we paid it; and we now really do have our building permit as of May 16th.